DPC assisted in conception and execution of an EPC contract for 50,000 barrels per day loading upgrade by installing 3 ea- 2500bph transfer pumps to 2 new 65,000 barrel capacity tanks. The project included design, engineering, fabrication, and installation of all associated piping, electrical, and equipment foundations. DPC fabricated and installed the piping manifold systems and revised the existing pipe to accomodate the upgrade. The new electrical system included an electrical building to house the 1200 amp service and VFD’s for the transfer pumps. DPC’s control group replaced the site’s programming software with ClearSCADA technology incorporated into their PLC. In the end, site operations are able to run the new system from the touch screen HMI located in their office.